How much gravel for a shed base?
Short answer
2.8 tons of crushed stone
for a 10 × 12 ft shed on a 4 in pad that runs 1 ft past the walls on every side (12 × 14 ft). Order 3.0 tons.
How the math works
- Pad size = shed + 1 ft each side: 10 × 12 becomes 12 × 14 ft = 168 ft².
- Volume at 4 in: 168 × 4 ÷ 12 = 56 ft³ = 2.07 yd³.
- Crushed stone weighs about 1.35 tons per yd³, so 2.07 × 1.35 = 2.8 tons.
- Round up to the next ½ ton when you order.
Crushed stone for a shed pad (1 ft border on every side)
| Shed | Pad | 4 in deep | 6 in deep |
|---|---|---|---|
| 8×10 ft | 10×12 ft | 2.0 tons | 3.0 tons |
| 10×12 ft | 12×14 ft | 2.8 tons | 4.2 tons |
| 10×16 ft | 12×18 ft | 3.6 tons | 5.4 tons |
| 12×16 ft | 14×18 ft | 4.2 tons | 6.3 tons |
| 12×20 ft | 14×22 ft | 5.1 tons | 7.7 tons |