A traditional sand and cement screed is sharp sand and cement mixed semi-dry, then compacted and levelled over a concrete slab or insulation. This calculator works out the cement in 25 kg bags and the sharp sand in tonnes for the mix you choose, or the number of pre-mixed screed bags.
Worked example: a 4 m × 3 m room, 65 mm deep, 1:4
- Volume: 4 × 3 × 0.065 = 0.78 m³. Add 10%: 0.86 m³.
- Dry materials: 0.86 × 1.25 = 1.07 m³ (semi-dry screed compacts as you lay it), split into 1 part cement and 4 parts sand.
- Cement: 1.07 ÷ 5 × 1,440 kg = 309 kg, so 13 bags of 25 kg. Sharp sand: 1.07 × 4/5 × 1.6 t = 1.37 tonnes.
- Pre-mixed instead: 0.86 m³ × about 2 tonnes ÷ 25 kg = 69 bags.
How deep should screed be?
- Bonded directly to a clean concrete slab: often around 25 to 40 mm.
- Unbonded on a damp-proof membrane: around 50 mm or more.
- Floating over insulation or underfloor heating pipes: around 65 mm or more (75 mm for heavier use).
- Measure the depth in a few places; old floors are rarely level, so use the average.
Which mix?
| Mix (cement : sharp sand) | Use |
|---|---|
| 1:3 | Stronger screed, often over underfloor heating |
| 1:4 | Standard floor screed |
| 1:5 | Light levelling where strength isn't critical |
Tips
- Sharp sand (concreting sand), not soft building sand.
- Semi-dry mix: it should hold together when squeezed in your hand without water running out.
- Drying time: a common rule is about 1 day per mm for the first 40 mm before laying moisture-sensitive floors; check with a moisture meter.
Common mistakes
- Ordering sand for the laid volume only. Semi-dry screed compacts, so you need more loose material than the finished volume.
- Laying it too thin over insulation, where it can crack.
- Using building sand, which makes a weak, dusty screed.
Questions people ask
How much sand and cement do I need for screed?
For a 1:4 mix, about 14 bags of 25 kg cement and 1.6 tonnes of sharp sand per m³ laid, before any extra for waste.
How many bags of cement for 1 m³ of screed?
About 18 bags at 1:3, 14 at 1:4 and 12 at 1:5 (25 kg bags), by this estimate.
What is the mix ratio for floor screed?
1:3 to 1:5 cement to sharp sand by volume; 1:4 is the usual choice.
How many bags of pre-mixed screed do I need?
Roughly volume (m³) × 2,000 ÷ 25. A 0.78 m³ floor needs about 63 bags, plus extra for waste.